NTPC share news, announcements and annual reports
NSE: NTPCBSE: 532555PowerLarge Cap
Share price at the NSE close on 2 Nov 2026. Previous close ₹316.25.
2 Nov: open ₹319.95, high ₹328.00, low ₹319.00
- Market capMarket capitalisation. Share price times the number of shares: what the whole company is worth at the day's price. The rank is by average market value over the six months to Jun 2026, among listed companies. Market capitalisation: how it is worked out
- ₹3,13,202 Cr20th largest listed
- P/EPrice to earnings, trailing. Market cap divided by the profit of the last twelve months (the latest four quarters, or two half years for a company that reports half-yearly) that belongs to the company's own shareholders, after the share of the other owners of its subsidiaries: what investors pay for each rupee of a year's profit. Price to earnings, trailing: how it is worked out
- 10.54
- P/BPrice to book. Market cap divided by the net worth that belongs to the company's own shareholders, its assets less everything it owes and less the other owners' share of its subsidiaries, on its latest balance sheet. Price to book: how it is worked out
- 1.47
- Dividend yieldDividend yield. Dividends paid per share in the twelve months to the day, as a percentage of the day's share price.
- 2.79%
- ROEReturn on equity. Profit over the last twelve months (the latest four quarters, or two half years for a company that reports half-yearly) that belongs to the company's own shareholders, as a percentage of their net worth, the money they have in the business. Net worth is the average of the latest balance sheet and the one a year before it.
- 14.7%
- ROCEReturn on capital employed. Operating profit after depreciation (revenue less operating expenses and depreciation, without other income and one-off items) as a percentage of all the money the business runs on: the whole group's net worth, the other owners of its subsidiaries included, plus borrowings. Lease liabilities are not counted: the results filings do not state them. The profit is over the last twelve months (the latest four quarters, or two half years for a company that reports half-yearly); net worth and borrowings are on the latest balance sheet.
- 8.2%
- Debt to equityDebt to equity. Borrowings divided by the whole group's net worth, the other owners of its subsidiaries included: rupees borrowed for each rupee of equity in the business. Lease liabilities are not counted: the results filings do not state them. From the balance sheet at the end of Sep 2026.
- 1.24
- Volume, NSEVolume. Shares traded on the last trading day; delivery is the part buyers kept rather than sold again the same day. Volume in the glossary
- 1,42,49,38554.9% delivered
NTPC share news and announcements
1,744 announcements, routine notices left out, newest first. Page 29 of 35.
Jun 2013
May 2013
24 May · Updates
As per the direction(s) given by Ministry of Corporate Affairs(MCA) vide orders dated December 20, 2012 and January 21, 2013 a meeting of equity shareholder of NTPC Limited held on May 24, 2013 for considering, and if thought fit, approving, with or without modification(s), the Scheme of Amalgamation of NTPC Hydro Limited, a wholly owned subsidiary of NTPC Limited with NTPC Limited. Since the counting of the votes and verification of the ballot papers will take some time, the result of the poll will be put up at the Registered office of the company at 5.00 pm on May 27, 2013 and on the website of the Company.10 May · Dividend
Board of Directors of the Company at its meeting held on May 10, 2013, inter alia, have recommended final dividend of Rs. 2.00 per equity share(including special dividend of Rs.1.25 per equity share) for the financial year 2012-13 , in addition to the interim dividend of Rs. 3.75 per equity share for the financial year 2012-13 paid in March 2013.10 May · Results
Consolidated Results for the year ended on 31-MAR-2013 as follows: Net Sales of Rs. 6795289 lacs for year ending on 31-MAR-2013 against Rs. 6495832 lacs for the year ending on 31-MAR-2012. Net Profit / (Loss) of Rs. 1259078 lacs for the year ending on 31-MAR-2013 against Rs. 981279 lacs for the year ending on 31-MAR-2012.10 May · Results
Standalone Results for the year ended on 31-MAR-2013 as follows: Net Sales of Rs. 6431638 lacs for year ending on 31-MAR-2013 against Rs. 6114489 lacs for the year ending on 31-MAR-2012. Net Profit / (Loss) of Rs. 1261939 lacs for the year ending on 31-MAR-2013 against Rs. 922373 lacs for the year ending on 31-MAR-2012.
Apr 2013
26 Apr · Updates
Unit-III of 500 MW of Indira Gandhi Super Thermal Power Station at Jhajjar of Aravali Power Company Private Limited a joint venture of NTPC Limited, Haryana Power Generation Corporation Limited, Govt. of Haryana and Indraprastha Power Generation Company Limited, Govt. of Delhi is declared on commercial operation w.e.f. 00:00 Hrs of April 26, 2013. With this the total commercial capacity of Indira Gandhi Super Thermal Power Station has become 1,500 MW and that of NTPC Group 39,684 MW.26 Apr · Board meeting
To, inter alia, consider, approve and take on record the Annual Financial Results for the financial year ending on March 31, 2013 after these results are reviewed by the Audit Committee of the Board. Further, the Board of Directors shall also consider recommendation of final dividend and special dividend, if any, on the equity shares capital of the company for the year 2012-13 in the same Board Meeting.1 Apr · Updates
The 5 MW Solar PV Power Station at Andaman & Nicobar Islands is declared for commercial operation w.e.f. 00:00 Hrs of March 31, 2013. With this the total capacity of non-conventional energy projects of NTPC Ltd. has become 10 MW. The total commercial capacity of NTPC has become 34820 MW and the total commissioned capacity of NTPC Group becomes 41184 MW. During the financial year 2012-13, NTPC has added 4170 MW which is the highest ever capacity addition by NTPC in any financial year.1 Apr · Updates
Unit-II of 500 MW of Mouda Super Thermal Power Project, Stage-I has been commissioned on March 29, 2013 at 18:23 hrs. With this the total installed capacity of Mouda Super Thermal Power Project has become 1000 MW and the total installed capacity of NTPC group has become 41174 MW.1 Apr · Updates
The 5 MW Dadri Solar PV Power Station is declared for commercial operation w.e.f. 00:00 Hrs of March 30, 2013. This is the first non-conventional energy project of NTPC Ltd. marking its foray into generation of renewable energy. With this the total commercial capacity of NTPC has become 34815 MW and the total commissioned capacity of NTPC Group becomes 41179 MW.
Mar 2013
25 Mar · Updates
Unit-II of 500 MW of Vindhyachal Super Thermal Power Station, Stage-IV has been commissioned on March 22, 2013 at 21:30hrs. With this the total installed capacity of Vindhyachal Super Thermal Power Station has become 4260 MW and the total installed capacity of NTPC group has become 40674 MW.13 Mar · Updates
Unit I of 500 MW of Mauda Super Thermal Power Station, Stage-I is declared for commercial operation w.e. f. 00:00 Hrs of 13.03.2013. With this the total commercial capacity of NTPC has become 34810 MW.1 Mar · Updates
Unit I of 500 MW of Vindhyachal Super Thermal Power Station, Stage-IV is declared for commercial operation w.e.f. 00:00 Hrs of March 01, 2013. With this the total commercial capacity of Vindhyachal Super Thermal Power Station has become 3760 MW and the total commercial capacity of NTPC has become 34310 MW.
Feb 2013
28 Feb · Updates
Unit II of 500 MW of Vallur Thermal Power Project of NTPC Tamil Nadu Energy Co. Ltd. a JV of NTPC Ltd. and TANGEDCO has been commissioned on February 28, 2013 at 02.20 Hrs.With this, the total installed capacity of Vallur Thermal Power Project has become 1000 MW and the total installed capacity of NTPC group has become 40174 MW.26 Feb · Board meeting
Board of Directors of the Company, at its meeting held on February 26, 2013, had accorded the investment approval for the following : (1) Chatti-Bariatu Coal Mining Project having rated production capacity of 7 MTPA in the sate of Jharkhand at an appraised current estimated cost of Rs.1314.57 Crore: (2) Gadarwara Super Thermal Power Project Stage-I (2x800 MW) to be implemented in the state of Madhya Pradesh at an appraised current estimated cost of Rs.11638.55 Crore subject to environmental clearance of Ministry of Environment and Forests.26 Feb · Dividend
Date of payment / despatch of dividend shall be March 12, 2013.26 Feb · Dividend
Board of Directors of the Company at its meeting held on February 26, 2013 have decided, inter-alia, to pay interim dividend at the rate of 37.5% (Rs.3.75/- per share) on the face value of paid-up equity shares of Rs.10/- each for the financial year 2012-13.18 Feb · Corporate action
Company has fixed Record Date as March 04, 2013 for the purpose of ascertaining the eligibility of the shareholders for payment of interim dividend, if declared by the Board.18 Feb · Board meeting
Inter-alia, to consider declaration of interim dividend for the year 2012-13.9 Feb · Updates
Nabinagar Power Generation Company Private Limited ,a Joint Venture of NTPC Ltd and BSEB, Bihar has achieved financial closure for Nabinagar Super Thermal Power Project consisting of three units of 660 MW each. The project is situated in the Aurangabad district of Bihar. A loan agreement for Rs 8775 crore in this regard was signed on February 08, 2013 with Rural Electrification Corporation Ltd. The loan would be utilised for financing capital expenditure of Nabinagar Super Thermal Power Project.6 Feb · Updates
Company has signed on January 29, 2013, a term loan agreement for USD 250 million with State Bank of India, New York Branch and Mizuho Corporate Bank, Limited., Singapore Branch as Arrangers and Lenders. The proceeds of the loan shall be utilized towards capital expenditure for procurement of goods and services for the ongoing and new projects and renovation and modernization of stations of the company. The loan carries a floating rate of interest linked to LIBOR and has a door to door maturity of 7 years.6 Feb · Updates
Government of India, through letter dated February 05, 2013, has conveyed the approval of the Government for settlement of dues of DESU period which, inter-alia, provides for payment to be made by Government of National Capital Territory of Delhi to NTPC of Rs. 2520.08 crore (comprising Rs. 835.97 crore as principal and Rs. 1684.11 crore as interest).5 Feb · Management
Consequent upon nomination as a Member of Fourteenth Finance Commission vide Presidential Notification No.10(2)-B(S)/2012 dated January 02, 2013, Dr. M. Govinda Rao, Independent Director has resigned from the Board of Directors of the Company w.e.f February 04, 2013.
Jan 2013
23 Jan · Updates
Ministry of Coal, Government of India through letter dated January 23, 2013, has conveyed the decision to withdraw the de-allocation of Kerandari, Chatti Bariatu and Chatti Bariatu (South) coal blocks, de-allocated vide their earlier letter dated June 14, 2011.22 Jan · Board meeting
Board of Directors of the Company at its meeting held on January 21, 2013, has accorded approval for equity investment of up to Rs. 2269.75 Crore in Nabinagar Power Generating Company Private Limited (NPGCPL), (A JV of NTPC and Bihar State Electricity Board with 50:50 participation) to enable it to implement Nabinagar Super Thermal Power Project (3X660 MW) in Aurangabad District of Bihar.21 Jan · Results
Standalone Results for the quarter ended on 31-DEC-2012 as follows: Net Sales of Rs. 1577491 lacs for the quarter ending on 31-DEC-2012 against Rs. 1611967 lacs and Rs. 1533230 lacs for the quarters ending on 30-SEP-2012 and 31-DEC-2011 respectively. Net Profit / (Loss) of Rs. 259676 lacs for the quarter ending on 31-DEC-2012 against Rs. 314235 lacs and Rs. 213039 lacs for the quarters ending on 30-SEP-2012 and 31-DEC-2011 respectively.11 Jan · Board meeting
Inter-alia, to approve and take on record the Un-audited Financial Results for the nine months period ended December 31, 2012 and Un-audited Financial Results for the quarter and nine month period ended December 31, 2012 after these results are reviewed by the Audit Committee of the Board.
Nov 2012
29 Nov · Updates
Unit I of 500 MW of Vallur Thermal Power Project of NTPC Tamil Nadu Energy Co. Ltd. a JV of NTPC Ltd. and TNEB is declared on commercial operation w.e.f. 00:00 Hrs of November 29, 2012. With this the total commercial capacity of Vallur Thermal Power Project has become 500 MW and that of NTPC Group - 38,174 MW.19 Nov · Updates
Unit # 5 of 500 MW of Rihand Super Thermal Power Station is declared for Commercial Operation w.e.f. 00:00 Hrs of November 19, 2012. With this the commercial capacity of Rihand STPS will reach 2500 MW and that of NTPC Group will be 37674 MW.8 Nov · Board meeting
Board of Directors of the Company at their meeting held on November 07, 2012 has accorded the investment approval for the Lara Super Thermal Power Project, Stage-I (2 X 800 MW) to be implemented in the state of Chhattisgarh at an appraised current estimated cost of Rs.11,846.00 Crore subject to environmental clearance of Ministry of Environment and Forests (MOEF).8 Nov · Updates
In line with the Corporate Disclosure requirements, we wish to inform you that the Unit-Ill of 500 MW of Indira Gandhi Super Thermal Power Project at Jhajjar of Aravali Power Company Private Limited (APCPL) a JV of NTPC Limited, Haryana Power Generation Corporation Limited and Indraprastha Power Generation Co. Ltd. has been commissioned on 07.11.2012 at 01:25 PM. With this, the total capacity of NTPC group has become 39,674 MW.With the coming of Unit-Ill, the total installed capacity of Indira Gandhi Super Thermal Power Project has become 1,500 MW
Oct 2012
26 Oct · Results
Standalone Results for the quarter ended on 30-SEP-2012 as follows: Net Sales of Rs. 1611967 lacs for the quarter ending on 30-SEP-2012 against Rs. 1595996 lacs and Rs. 1537754 lacs for the quarters ending on 30-JUN-2012 and 30-SEP-2011 respectively. Net Profit / (Loss) of Rs. 314235 lacs for the quarter ending on 30-SEP-2012 against Rs. 249867 lacs and Rs. 242412 lacs for the quarters ending on 30-JUN-2012 and 30-SEP-2011 respectively.12 Oct · Board meeting
Un-audited financial results of the Company for quarter and half-year ending September 30, 2012 shall be considered, approved and taken on record, after these results are reviewed by the Audit Committee of the Board.
Sep 2012
28 Sep · Updates
Unit #4 of 500 MW of Simhadri Super Thermal Power Station is declared under Commercial Operation w.e.f. 00:00 Hrs of September 30, 2012. With this the commercial capacity of Simhadri STPP will reach 2000 MW and that of NTPC Group will be 37174 MW26 Sep · Updates
NTPC Limited priced on September 24, 2012, USD 500 million Fixed Rate Senior Unsecured Notes under its USD 2 billion MTN Programme. The Notes carry a coupon of 4.75 per cent per annum payable semiannually and are of 10 year tenor. The proceeds would be used to finance capital expenditure of ongoing and/or new power projects of the company.20 Sep · Disclosure of Voting Pattern - Clause 35A
18 Sep · Meeting
At the Annual General Meeting of the Members of the Company held on September 18, 2012, the shareholders of the Company have approved final dividend @ Rs.0.50 per share. The total dividend (including interim dividend) for the financial year 2011-12 is Rs.4.00 per share (face value Rs.10/- each). The date of payment/ dispatch of dividend shall be September 25, 2012.
Aug 2012
22 Aug · Meeting
Register of Members & Share Transfer Books of the Company will remain closed from September 08, 2012 to September 18, 2012 (both days inclusive) for the purpose of Payment of Dividend & Annual General Meeting (AGM) of the Company to be held on September 18, 2012. Further, It is intimated that the dividend on equity shares, as recommended by the Board of Directors, subject to the provisions of section 206A of the Companies Act, 1956, if declared at the Annual General Meeting, will be paid on September 25, 2012.